Why Lopez Road Is Down to One Lane, and Which Pebble Beach Streets Are Next

If every household in the Del Monte Forest pays for burying the power lines, whose street goes first? Mike Niccum, then general manager of the Pebble Beach Community Services District, said that was the question once undergrounding was to be paid for through property taxes, according to a Monterey County Weekly cover story on Peninsula storm damage. The district decided to start with the main feeder lines. Because of that choice, you've been waiting for flaggers on Lopez Road since September, and the Lopez and Sunridge corridor is set to be the busiest stretch of pavement in the forest this winter.

What the crews on Lopez Road are building

Phase IV of PBCSD's Undergrounding Overhead Utilities Program began on September 8, 2026, on Lopez Road near the Pebble Beach Fire Station. The contractor, Outsource, spent September potholing to verify existing utilities. It then dug out utility vaults along Lopez from the PBCSD office up to Poppy Hills golf course and began laying out the joint trench in mid-October. The trench will run vault to vault and will hold PG&E power, AT&T phone and Comcast cable lines together. Every week, district staff meet with engineers from the Wallace Group and Outsource's crew to review progress. Principal Engineer Chris Simmons's October 30 report to the board said Outsource expected to stay on Lopez Road "for the next several weeks."

Here is what that means for your drive:

  • Hours: Monday through Friday, 8:00 a.m. to 5:00 p.m.
  • Traffic: one-lane traffic control in the active work area.
  • Route: up Lopez, onto Sunridge and Ronda, around Spruance and down to Del Ciervo. The Phase IV project page also lists Midwood Lane and Atajo Way.
  • Timeline: about 24 months of trenching. After that, AT&T, Comcast and PG&E pull their lines through, and the overhead lines and poles come down at the end of the project, which is slated for 2028.

So far the district has posted a start date only for Lopez Road. Every other street on the project page still shows TBD, so the poles on Ronda or Del Ciervo will be standing for a while yet.

Why the feeder goes first

Pebble Beach has about 60 miles of power lines, according to the Weekly's reporting. The program doesn't cover all of them. It targets 12 miles of primary power and communication main lines. Those are the trunks that feed everything else. A tree on a main line can black out a large share of the forest, while a tree on a side street darkens fewer homes.

The geography makes outages here worse. Niccum told the Weekly that outages in Pebble Beach tend to last longer than elsewhere on the Peninsula. Because the area is less populated, PG&E restores higher-population areas first. Crews also have to treat downed lines as live until they're de-energized, and some of the forest's hills and gullies are hard for trucks to reach. Burying the feeders first gives the most homes the most protection per mile of trench.

The district counts Phases I through III as six miles, which is a little over half the primary distribution system. Phase III ran along Forest Lake, Drake, Ondulado, Alva, Sombria and Portola. Once Phase IV is finished, the district says only about two miles will remain for Phase Five.

The price tag residents balked at in 1996

The Weekly traced the program to 1996, when power outages led district leaders to survey residents on whether they would tax themselves to bury the lines. The estimate at the time was about $1 million a mile.

"People did a quick calculation and said a generator would be much cheaper than that," Niccum told the Monterey County Weekly. "Undergrounding is a great idea when someone else is paying for it."

After a large storm outage in early 2008, the Weekly reported, residents were more open to the idea. In 2011, the Local Agency Formation Commission approved PBCSD's authority to underground power and communication lines in Pebble Beach, with the work paid for through property taxes. The district's own history dates board activation to June 24, 2011, with pay-as-you-go construction beginning in 2012.

Pay-as-you-go explains the pace. When the Weekly story ran, the first three phases had cost about $18 million, each had taken three to four years, and the most recent had cost about $3.5 million a mile. That's more than triple the 1996 estimate. The PG&E Rule 20A program, which helps fund undergrounding done for aesthetic reasons, didn't apply because Pebble Beach's goal was reliability.

Part of the cost is coordination. Every buried mile involves three utilities, and each one charges for its share. On September 25, the PBCSD board voted 5-0 to authorize a payment of up to $225,000 for Comcast's Phase IV utility fee. Niccum also pointed to existing underground infrastructure, such as sewer lines, as one more thing crews have to work around. This winter, some of those sewer lines are being dug up too.

The sewer job lands on the same streets

PBCSD replaces about a mile of sewer pipe in an average year. This year's project covers about two miles. Bids opened on October 20. KJ Woods Construction of South San Francisco came in lowest at $1,948,000, below the engineer's estimate of $2,235,000 and well below the $2,946,730 high bid. District staff recommended the award for the October 30 board meeting and expect construction to start in December 2026 and take six months.

The district says it will notify residents before work starts near their property. You'll still be able to drive to your home, and sewer service will continue throughout. When the project wraps up in summer 2027, about 20 percent of the community's 83 miles of sewer main will have been rehabilitated.

Sunridge Road and Atajo Way appear on both the Phase IV route and the sewer bid list:

Location Undergrounding Phase IV 2026–27 sewer replacement
Lopez Road Under way since Sept. 8 Not listed
Sunridge Road Start TBD Listed, expected from December
Atajo Way Start TBD Listed, expected from December
Ronda, Spruance, Midwood Lane, Del Ciervo Start TBD Not listed
Sunset Lane and the easement south of it Not listed Listed
Mission Road and the MPCC maintenance yard Not listed Listed
Hermitage Road to Stevenson Drive Not listed Listed
Oleada Road to Riata Road Not listed Listed
Cypress Drive to Cabrillo Road easement Not listed Listed
MPCC 9th hole and Pebble Beach Golf Links 2nd fairway easements Not listed Listed

The station on the coast that can't be switched off

The third project is out of sight from most driveways. The Seal Rock pump station sits underground on the 17-Mile Drive shoreline, north of Seal Rock. It's the largest of the district's eight lift stations and pumps two-thirds of Pebble Beach's wastewater up Spyglass Hill Road to the Carmel Area Wastewater District for treatment.

"The pump station cannot be shut down," Simmons said in the district's Fall/Winter 2026 newsletter. In normal operation, two of its six pumps run constantly, two more kick in for high flows or a failure, and the last two are a third backup. To keep all three levels of redundancy during the rebuild, the district brought in two trailer-mounted pumps that run on the surface.

Contractor Laurel Ag and Water is replacing the pumps one set at a time. The middle set was scheduled for commissioning on November 3, followed by a week of test running before the second set comes out. District staff expect Laurel to keep working through the winter and into 2027 on the last two pump sets and a new surge tank.

Your winter calendar around the work

The busy corridor is also where the holiday trees go. Through January 31, you can drop off a tree of any size, uncut, at the Pebble Beach Company Corporation Yard at Lopez and Sunridge Roads. That puts you on the same stretch where the trench work started. If that corner is slow going, curbside tree pickup runs Monday, January 4, through Friday, January 15, on your regular collection day. Cut trees taller than six feet into segments, remove all lights and decorations, and keep flocked trees out.

GreenWaste Recovery's holiday schedule pushes pickup back one day on these dates:

  1. Thursday, Nov. 26 moves to Friday, Nov. 27
  2. Friday, Nov. 27 moves to Saturday, Nov. 28
  3. Friday, Dec. 25 moves to Saturday, Dec. 26
  4. Friday, Jan. 1 moves to Saturday, Jan. 2

Any bulky-item pickups you haven't used for 2026 expire at year's end. On January 1, each household goes back to three. Extra-material stickers expire December 31, and 30 new ones arrive by mail in January. To book a pickup, call GreenWaste at (831) 920-6707.

When you're planning a weekday errand along Lopez, remember that the flaggers work 8 to 5, Monday through Friday, and that the sewer crews are expected to join them on Sunridge in December.

Thinking about selling a home on Sunridge, Ronda or Del Ciervo while the trenches are open? A buyer's first visit may come with a flagger and a one-lane approach, and that changes how you plan showings and timing. Peter Boggs keeps up with the forest's project schedules and can help you plan a listing around them. Contact Peter.